Programme Dashboard
AURA Maldives MVAC Installation Programme — Client: JD Dhigu Dhefaru Pvt Ltd · Combined value: $981,670 · Duration: Feb 2026 – Jun 2027

Readiness Pipeline 0 buildings

Material Supply Chain

Progress by Phase

Next Actions Urgent items

    Upcoming Payment Milestones

    InvoiceContractDescriptionAmountStatus
    Site Readiness
    Is each location physically ready for MVAC installation? Tick every item before assigning a team.
    Readiness gates team assignment. A team can be assigned only once a location’s checklist is complete. Readiness is site-readiness only — it is independent of material delivery, so teams mobilise and start with currently-supplied materials before the balance arrives.
    Buildings Register
    All structures by zone with readiness state and progress
    Building Zone Units State Team Progress Action
    Drawings
    MVAC layout drawings per building — uploaded PDFs & images for zone detection and scope
    Work Scope
    Per-equipment installation progress, built from detected drawing zones — rolls up to the building & dashboard
    Takeoff & Reconciliation
    Per-building materials (BOQ) + equipment counts cross-checked against drawings (PDF/CAD)
    Materials
    Procurement & stock ledger reconciled against the BOQ — what to order, what's pending, what's on site
    Material Unit Required Ordered Delivered Used Available To Order Pending Status
    Commercials
    Three contracts covering SP1 (Materials), SP2 (Labour), SP3 (Interlock)

    Invoicing by Contract

    Programme Schedule
    Critical-path schedule computed from the task register — linked to live site progress
    0% overall

    Phases

    Tasks — CPM Gantt red = critical path · 🔗 = auto-driven by site data · click ✎ to edit

    Schedule Summary

    Task Register
    Execution task register — 56 sub-tasks across 8 phases (WBS 0–7)
    0% complete
    Install Teams
    Create groups, add people, assign teams to ready buildings
    Snag List
    Defects and punch list items logged during installation

    No Snags Recorded

    Installation has not started yet. Snags will be logged once on-site works begin.