Dashboard
AURA Maldives MVAC installation — where the site stands today, what needs a decision, and what is on its way.

Next Actions

    Installation by Zone 0%

    Cumulative Progress — Planned vs Actual

    Readiness Pipeline 0 buildings

    Progress by Building

    Deliveries

    Progress by Phase

    Upcoming Payment Milestones

    InvoiceContractDescriptionAmountStatus
    Site Readiness
    Is each location physically ready for MVAC installation? Tick every item before assigning a team.
    Readiness gates team assignment. A team can be assigned only once a location’s checklist is complete. Readiness is site-readiness only — it is independent of material delivery, so teams mobilise and start with currently-supplied materials before the balance arrives.
    Drawing Sets
    MVAC drawing PDFs for site reference. Tap any sheet to open it in your device’s PDF viewer — lightweight, no zone processing.
    Correspondence
    Formal client letters on the Nimmin letterhead — RFI, RFA, Site Instructions, NCR, transmittals & general letters, with a tracked register.
    No.TypeSubjectToDateStatus
    EOT / Claims Register
    Extension-of-time and cost claims — notice, particulars deadline, determination. FIDIC-style: late particulars can time-bar the claim.
    RefTypeTitle / causeNoticeParticulars dueDaysAmountStatus
    Buildings Register
    All structures by zone with readiness state and progress
    Building Zone Units State Team Progress Action
    Drawings
    MVAC layout drawings per building — uploaded PDFs & images for zone detection and scope
    Pre-Commissioning — VRV Systems
    Daikin service handover checklist per system: 22 checks, nitrogen pressure test and vacuum test records. Print the Nimmin report or send it to the client portal as an inspection.
    Work Scope
    Per-equipment installation progress, built from detected drawing zones — rolls up to the building & dashboard
    Takeoff & Reconciliation
    Per-building materials (BOQ) + equipment counts cross-checked against drawings (PDF/CAD)
    Materials
    Procurement & stock ledger reconciled against the BOQ — what to order, what's pending, what's on site
    Material Unit Required Ordered Delivered Used Available To Order Pending MAR PO # Status
    Commercials
    Contracts, invoices, variations & milestone billing

    Invoicing by Contract

    Programme Schedule
    Critical-path schedule computed from the task register — linked to live site progress
    0% overall

    Phases

    Tasks — CPM Gantt red = critical path · 🔗 = auto-driven by site data · click ✎ to edit

    Schedule Summary

    My Work
    Your team’s buildings — tap a step to update progress, add photos as you go
    Progress Claims — Contract Programme
    SP2 labour programme — earned value auto-computed from site scope data, bill weights per the agreed claim basis

    S-Curve — planned vs earned planned = bill-weighted baseline · earned = certified claimable progress

    Activity register — plan vs actual 🔗 = auto from site scope · type in the Done % column for manual activities

    Installation Schedule — By Building
    Planned window per building vs live installation progress (plan % assumes linear progress across the window). PM / admin assign teams and set start + duration (finish auto-adjusts); progress comes from site data.
    BuildingZoneTeamPlanned StartPlanned FinishDurationPlan %Actual %ΔStatus
    Task Register
    Execution task register — 56 sub-tasks across 8 phases (WBS 0–7)
    0% complete
    Project Team
    Key personnel assigned to the project — PM, Site Supervisor, QA/QC and others (separate from install teams)
    Install Teams
    Create groups, add people, assign teams to ready buildings
    Snag List
    Defects and punch list items logged during installation
    ⚠

    No Snags Recorded

    Installation has not started yet. Snags will be logged once on-site works begin.

    User Management
    Nimmin spine users (shared with the HR app) — one login across all apps. Aura Role controls rights here.
    NameEmailDivisionHR RoleAura RoleCommercials